2008 CALENDAR
|
January 11 |
Recommended deadline for LFCCs to advertise for 2008 PCFO applications via Public Notice. The application period must be open a minimum 21 calendar days, but it is recommended that it remain open for 30 calendar days. -- 5 CFR §950.104(c) |
|---|---|
| 15 | Closing date for National/International Independent Organization applications (Must be received in CFC Office no later than 5:00pm EST. Late applications will not be considered) |
| 31 | Closing date for National/International Federation applications (Must be received in CFC Office no later than 5:00pm EST. Late applications will not be considered.) |
|
February 15 |
Recommended deadline for 2008 PCFO Applications to the LFCC. |
| 29 | Deadline for Submission of Form 1417 (2007 campaign results) to OPM. |
|
March 10 |
Recommended opening date for 2008 local applications. (Recommended date only – LFCCs may determine the application period dates for their individual campaign—however, all local application decisions must be completed by the LFCC no later than May 2, 2008.) |
| 11-14 | CFC Regional Workshop in Orlando, FL |
| 17 | Deadline for LFCCs to select a PCFO – 5 CFR §950.801(a)(3) |
| Deadline for PCFOs to forward to designated agencies the 2007 donor information (names, addressees, and/or contribution amounts as authorized) who wish to receive acknowledgement of their gift. -- 5 CFR §950.601(c) | |
| Deadline for PCFOs to forward “accounting” letters (amounts designated and undesignated) to designated charities and/or federations. – 5 CFR §950.901(i)(1) | |
| 31 | Deadline for PCFOs to make final disbursement of 2006 campaign funds. |
|
April 1 |
Deadline for all campaigns to begin disbursement of 2007 campaign funds. – 5 CFR §950.901(i)(2) |
| 13-16 | CFC Regional Workshop – Las Vegas, NV |
| 14 | Deadline for 2008 Local application period. Campaigns may set an earlier application deadline. Local organizations should contact their local CFC office for more information. |
| 30 | Target date for notice of national/international organization eligibility decisions. |
|
May 2 |
Deadline for LFCC to notify local organizations of eligibility decisions in writing. -- 5 CFR §950.204(e) |
| 23 | LFCCs begin receiving appeals within seven (7) business days of the date of receipt of the initial LFCC decision or fourteen (14) calendar days from the date the decision was mailed, whichever is earlier. |
|
June 2 |
Deadline to submit Annual E-Technology Report to OPM. |
| 16 | Deadline for decisions by LFCC on all local organization appeals. |
| 30 | Target date for completion of 2008 National/International List of Participating Agencies (sent to campaigns via email and posted on OPM website) |
| 31 | Target date for OPM to complete Local appeals. |
|
August 1 |
2008 CFC Audit Guide reports and supporting documentation must be submitted to the LFCC. |
| September 1 - December 15 | 2008 Combined Federal Campaign Official Solicitation Period. -- 5 CFR §950.102(a) |
|
September 15 |
Deadline for LFCCs to send copies of the 2008 CFC Audit Guide and supporting documentation to OPM. |
|
October 2 |
Kick-off |
|
December 1 |
OPM will begin to accept 2009 National/International Applications |